Twenty-year-old roofs caused leaking at Community Consolidated School District 89’s Arbor View and Westfield elementary schools and Glen Crest Middle School.
CCSD 89 tasked Legat’s Special Projects team with the design of roofing removal and replacement at the three schools. The resulting new single-ply EPDM roofing eliminates the leaks and extends the roof service life for another 20 years. Additionally, the increased insulation enhances energy efficiency, reduces heating and cooling costs, and improves indoor comfort for students and staff.
The work, totaling 196,000 square feet, was completed at all three schools over one summer.
Having worked with Legat for several years, I am so appreciative of their knowledge and expertise as well as their attention to detail. Whenever I have had any questions or concerns, they have always quickly responded. I’ve always been amazed at Legat’s breadth of knowledge in dealing with the building envelope.
Tim E. Tomazin, Director of Buildings and Grounds
– CCSD 89
Before and After
Roofing Replacement
Let’s Connect.
Your Vision Is Waiting To Be Explored.
Our team is ready to work with you to intersect your ideas with our expertise. Contact our professionals today to elevate your space.